Case Study | Workplace Decommission and Technical Removals
A Sixth-Floor Exit.
One Connected Assignment.
ASI connected furniture teardown, technical removals and building access coordination for Hanley Wood's sixth-floor Los Angeles office exit.
Overview
The Challenge
Furniture could leave the building only after 6 p.m. Workstation teardown, technical cabling and material handling had to fit that access rule while moving contents from a sixth-floor suite to the trucks.
ASI’s Approach
ASI organized the removal sequence around the evening access window and coordinated the interior crews, designated carts, floor protection and truck responsibilities. Cable removal remained part of the same assignment.
Project Info
- Client
- Hanley Wood
- Location
- Los Angeles, California
- Site
- 6222 Wilshire Boulevard
- Workplace
- Suite 600
- Delivery
- Office decommission
- Status
- Clearance completed
Office Clearance
From Furnished Workstations to Cleared Interiors.
Furniture and workstation clearance opened the workplace while existing carpet, fixed cabinetry and building finishes remained.
One Connected Assignment
Building Access, Teardown and Technical Removals.
Field Execution
The Hands-On Removal Work.
Workstation dismantling, cable removal and material handling remained part of the same workplace-exit assignment.
Completed Clearance
Existing Rooms and Finishes Retained.
The Result
A Connected Office Decommission.
The office was cleared of its furniture and workstation systems. The field sequence also records cable-removal work, while completed clearance views show the existing rooms and finishes retained. ASI gave the workplace team one accountable partner for the connected removal assignment, coordinating building access, hands-on teardown, technical removals and material handling.

Planning an Office Decommission?
Connect furniture clearance, technical removal responsibilities and building access through one coordinated assignment.