Case Study | Electrical and Low-Voltage Disconnection

Disconnect the Systems.
Keep the Exit Moving.

ASI coordinated furniture electrical disconnection and residual data removal for a time-sensitive Siemens workplace decommission in Buffalo Grove.

View Full Case Study PDF

Cover of the Siemens Buffalo Grove technical disconnection case study

The Workplace Context

The Connections Behind the Furniture.

A workplace exit depends on the connections behind the furniture. ASI handled a defined electrical and low-voltage removal phase at 1000 Deerfield Parkway, coordinating with Hilldrup before the next stage of the decommission.

Office workstations during the defined technical disconnection phase | In Progress

Furniture and workplace context | In Progress

Overview

The Challenge

Electrical disconnections emerged as an urgent dependency in a planned office decommission. The work crossed two floors, with power and data sharing furniture feeds and poles.

ASI's Approach

ASI clarified the power and data responsibilities, mobilized its field team and sequenced the second-floor work ahead of the first floor. One assignment connected the technical scope with the furniture-removal team.

Project Info

Client
Siemens
Location
Buffalo Grove, Illinois
Site
1000 Deerfield Parkway
Floors
First and second
Scope
Power and data removal
Partner
Hilldrup
Status
Defined technical phase completed

The ASI Approach

Technical Responsibilities, Connected.

Confirm the feed conditionsThe request covered approximately 65 furniture feeds across the two floors, including column-fed connections and power poles.
Close the scope interfacePower and data removal were brought into one defined assignment after the residual cabling was clarified.
Prepare the field teamCrew mobilization, site access and the required job documentation were coordinated for the Monday start.
Sequence the two floorsThe work order prioritized the second floor before the first, aligning the disconnect work with the wider decommission.
Document the completed phaseThe site contact and ASI field lead signed the completion work order for the technical assignment.

Technical Work in the Field

Power and Data at the Furniture Interface.

The Defined Phase

A Completed Technical Assignment.

ASI completed the defined electrical and low-voltage removal assignment across the two office floors. The completed field work order was signed by both the site contact and ASI lead.

All Solutions, Inc.

Planning an Office Decommission?

Connect furniture-removal dependencies with defined power and data responsibilities through one accountable project partner.