Case Study | Technical Decommission and Wall Restoration
Disconnect the Systems.
Restore the Finish.
ASI connected electrical disconnection, cable-removal work and wall restoration for a San Antonio office exit, including the added preparation and repainting behind a glued wall panel.
Overview
The Challenge
The exit combined electrical and data work with wall repairs, an evening removal restriction and changing site conditions. A glued wall panel added full-wall restoration to the assignment.
ASI's Approach
ASI coordinated technical and finishing crews, confirmed the final removal boundaries, and carried the added wall preparation and painting through closeout.
Project Info
- Client
- KPMG
- Location
- San Antonio, Texas
- Site
- 17802 IH-10, Suite 101
- Scope
- Technical work and restoration
- Interfaces
- Electrical, cabling and painting
- Delivery
- Coordinated office exit
- Status
- Technical and finishing assignment completed
The Workplace Context
The Existing Suite.
Technical Work and Finishing
Keep the Responsibilities Connected.
The assignment connected UPS disconnection, electrical safe-off, cable-removal work and wall repairs. ASI confirmed the final removal boundaries and coordinated the technical scope with a separately managed furniture decommission.
Wall Restoration
One Wall, Through Each Phase.
Removing the glued panel exposed a broader surface-restoration task. ASI carried that wall through preparation, refloating and repainting.
After the Assignment
Technical Work and Finishing, Closed Out.
Furniture decommission was managed separately from ASI's technical and finishing assignment.
The Result
One Accountable Technical and Finishing Partner.
ASI gave the workplace team one accountable partner for technical and finishing work, connecting revised scope decisions with field execution and closeout.

Planning an Office Exit?
Connect technical disconnection and restoration responsibilities through one accountable project partner.