U.S. Bank Encino Technical Workplace Decommission

Home > Projects > U.S. Bank Encino Technical...
U.S. Bank

Case Study | Technical Workplace Decommission

Disconnect.
Dismantle.
Clear the Workplace.

ASI brought furniture dismantling, electrical disconnection, cable removal and wall patching together for a U.S. Bank office exit in Encino.

View Full Case Study PDF

Cover of the U.S. Bank Encino Technical Workplace Decommission case study

Overview

The Challenge

Workstations, conference furniture and office equipment were connected to power and data. Their removal also left wall attachments, an IDF room and local water connections to address. A coordinated office exit needed the technical and physical work managed together.

ASI’s Approach

Working through Atlantic Relocation, ASI addressed the connections between the workplace and the building, then carried the removal scope through localized repair and cleanup.

Project Info

Client
U.S. Bank
Location
Encino, California
Site
15910 Ventura Boulevard, Suite 1712
Delivery partner
Atlantic Relocation
Scope
Technical workplace decommission
Status
Scope completed

Connected Workplace Systems

Clearing an Office Starts
With What Connects It.

Power and data served the workstations and conference furniture. ASI brought those technical connections into the same removal scope as the furniture, wall attachments and IDF equipment.

Electrical outlet boxes, power whip and data cable exposed at workplace furniture during dismantling | In Progress

Furniture-integrated electrical and data connections | In Progress

The ASI Approach

The Furniture Was Only
Part of the Removal.

ASI’s scope connected electrical disconnection, low-voltage removal, furniture dismantling and localized repairs within one coordinated office exit.

Disconnect workplace powerElectrical work addressed the connections serving cubicles, conference furniture and other affected areas before removal.
Remove workplace cablingThe scope followed low-voltage cabling from workstations and private offices back to the IDF, including uprights and patch-panel connections.
Dismantle furniture and the IDFFurniture dismantling was coordinated with removal of IDF racks and wall-mounted items, keeping the physical and technical scopes connected.
Address attachment pointsLocalized wall repairs followed removal of overhead storage, whiteboards and other mounted items. Patching also addressed the cleared IDF area.
Finish the defined removal scopeThe assignment included local water-line safe-off and a final broom sweep and clean. Existing flooring and surrounding finishes remained in place.

Technical Field Execution

Power, Data and Furniture Removal.

The Cleared Workplace

From Connections
to Localized Repairs.

The completed room photographs show cleared spaces and localized patches, with existing flooring and surrounding finishes retained.

Cleared office circulation after furniture removal with original flooring and surrounding finishes retained | Completed

Cleared circulation | Completed

Cleared Encino work area with localized wall patches and existing floor wear retained | Completed

Cleared work area and localized patches | Completed

Cleared IDF footprint with original surrounding wall and floor surfaces retained | Completed

Cleared IDF footprint | Completed

The Result

Connected Workplace Systems.
One Coordinated Exit.

Office areas were cleared of furniture and the workplace connections addressed. The result brought the technical and physical removal together while retaining the building’s existing surrounding finishes.

Coordinated responsibilities

The physical removal and its technical dependencies were managed within one ASI scope.

Power and data removal

The assignment connected electrical, low-voltage, furniture and localized repair work.

A cleared office

Completed room views show the cleared workplace after the furniture-removal scope.

Existing finishes retained

Localized repairs addressed removal points while retaining existing flooring and surrounding finishes.

All Solutions, Inc.

Planning a Workplace Transition?

Bring electrical disconnection, cable removal, furniture dismantling and localized repairs together through one accountable project partner.