All Solutions, Inc. (ASI) helps companies execute workplace projects without having to manage disconnected vendors, trades, and field teams on their own.

Follow Us

BlueGrace Burbank to Phoenix Workplace Reuse

Home > Projects > BlueGrace Burbank to Phoenix...
BlueGrace Logistics

Case Study | Workplace Relocation and Installation

Reuse the System.
Rebuild the Layout.
Adapt the Details.

ASI coordinated the teardown, preparation and reassembly of BlueGrace workstations between California and Arizona, including power-pole adaptations at the receiving office.

View Full Case Study PDF

Cover of the BlueGrace Burbank to Phoenix Workplace Reuse case study

Overview

The Challenge

Moving an existing workstation system meant more than transferring furniture. Components had to be disconnected, disassembled and prepared at the origin, then rebuilt to suit the Phoenix layout and ceiling conditions.

ASI’s Approach

ASI connected origin teardown and palletized staging with destination assembly. When the power poles required additional height, the field scope expanded to modify four poles for the receiving ceiling deck.

Project Info

Client
BlueGrace Logistics
Origin
Burbank, California
Destination
Phoenix, Arizona
Site
5415 E High Street, Suite 300
System
29 cubicles in the scope
Work phase
Workstation installation

The Receiving Workplace

Existing Workstations.
A New Office Arrangement.

The blue-and-white workstation system was reassembled in the Phoenix suite. Installation photographs show the furniture layout and the electrical access conditions during this phase; final building power connection was outside ASI's scope.

Workstation layout, power pole, open ceiling access and active installation ladder in the Phoenix suite | In Progress

Receiving layout and ceiling access | In Progress

The ASI Approach

Two Offices.
One Connected Field Sequence.

The assignment linked the Burbank teardown to the Phoenix installation. The sequence followed the same furniture system across preparation, handling and reassembly, with a field change for the receiving ceiling conditions.

Disconnect and dismantleDisconnect the existing cubicle feeds and safely isolate the affected power interface before dismantling the furniture system at the origin.
Prepare components for transportBand, palletize and stage the workstation components for the separate freight movement to the Phoenix destination.
Reassemble the workstation layoutAssemble the reused cubicle system in the receiving suite, coordinating the panels, work surfaces and furniture components.
Adapt the receiving interfacesModify four poles to reach the receiving ceiling deck, including the added material, labor and finish scope.
Coordinate the power interfaceRun and test workstation power within ASI's scope, with final building connection by others. A later service visit addressed a loose jumper and duplexes.

Workplace Reuse

The System, Reassembled.

The existing blue-and-white workstation system was reassembled in the Phoenix suite. ASI coordinated the furniture installation and receiving-site adaptations, with final building electrical connection and freight movement handled separately by others.

Reused blue-and-white BlueGrace workstations assembled in the receiving Phoenix office | In Progress

Phoenix workstation assembly | In Progress

The Origin Workplace

Prepare the Existing System.

At the Burbank office, ASI disconnected and dismantled the existing cubicle system, then banded, palletized and staged its components for the separate freight movement to Phoenix.

Existing BlueGrace blue-and-white workstations in the Burbank office before dismantling | Before

Burbank workstation system | Before

Field Adaptation

Connect the Installation Details.

Four power poles were modified to reach the receiving ceiling deck. ASI ran and tested workstation power within its defined installation scope, with final building connection by others. A later service visit addressed a loose jumper and duplexes within the installed system.

The Result

Furniture Reused.
Field Details Resolved.

Existing workstations were reassembled in Phoenix with adaptations for the receiving space. Furniture handling, power-pole changes and later service were coordinated around the same system.

Two-site continuity

Origin teardown and preparation were linked to the receiving installation.

Defined electrical responsibilities

ASI coordinated the workstation power interface with the separate final building connection.

A visible installation result

Field photographs document the assembled cubicle rows and adapted pole locations.

Support after the initial visit

A later service visit addressed a loosened workstation jumper and duplexes.

All Solutions, Inc.

Reusing Workstations in a Different Office?

Bring furniture preparation, installation and field adaptations together through one accountable project partner.

Discuss Your Project

View Full Case Study PDF

Explore ASI Projects

Ready to Move Your Project From Plan to Field?