Case Study | Workplace Relocation and Installation
Reuse the System.
Rebuild the Layout.
Adapt the Details.
ASI coordinated the teardown, preparation and reassembly of BlueGrace workstations between California and Arizona, including power-pole adaptations at the receiving office.
Overview
The Challenge
Moving an existing workstation system meant more than transferring furniture. Components had to be disconnected, disassembled and prepared at the origin, then rebuilt to suit the Phoenix layout and ceiling conditions.
ASI’s Approach
ASI connected origin teardown and palletized staging with destination assembly. When the power poles required additional height, the field scope expanded to modify four poles for the receiving ceiling deck.
Project Info
- Client
- BlueGrace Logistics
- Origin
- Burbank, California
- Destination
- Phoenix, Arizona
- Site
- 5415 E High Street, Suite 300
- System
- 29 cubicles in the scope
- Work phase
- Workstation installation
The Receiving Workplace
Existing Workstations.
A New Office Arrangement.
The blue-and-white workstation system was reassembled in the Phoenix suite. Installation photographs show the furniture layout and the electrical access conditions during this phase; final building power connection was outside ASI's scope.

Receiving layout and ceiling access | In Progress
The ASI Approach
Two Offices.
One Connected Field Sequence.
The assignment linked the Burbank teardown to the Phoenix installation. The sequence followed the same furniture system across preparation, handling and reassembly, with a field change for the receiving ceiling conditions.
Workplace Reuse
The System, Reassembled.
The existing blue-and-white workstation system was reassembled in the Phoenix suite. ASI coordinated the furniture installation and receiving-site adaptations, with final building electrical connection and freight movement handled separately by others.

Phoenix workstation assembly | In Progress
The Origin Workplace
Prepare the Existing System.
At the Burbank office, ASI disconnected and dismantled the existing cubicle system, then banded, palletized and staged its components for the separate freight movement to Phoenix.

Burbank workstation system | Before
Field Adaptation
Connect the Installation Details.
Four power poles were modified to reach the receiving ceiling deck. ASI ran and tested workstation power within its defined installation scope, with final building connection by others. A later service visit addressed a loose jumper and duplexes within the installed system.
The Result
Furniture Reused.
Field Details Resolved.
Existing workstations were reassembled in Phoenix with adaptations for the receiving space. Furniture handling, power-pole changes and later service were coordinated around the same system.
Two-site continuity
Origin teardown and preparation were linked to the receiving installation.
Defined electrical responsibilities
ASI coordinated the workstation power interface with the separate final building connection.
A visible installation result
Field photographs document the assembled cubicle rows and adapted pole locations.
Support after the initial visit
A later service visit addressed a loosened workstation jumper and duplexes.

Reusing Workstations in a Different Office?
Bring furniture preparation, installation and field adaptations together through one accountable project partner.