Case Study | Phased Workplace Reuse
Reuse The Workstations.
Coordinate The Power.
Manage The Sequence.
ASI combined workstation planning, dismantling, reassembly and electrical reconnection for a phased Cemex workplace assignment in Ontario.
Overview
The Challenge
Existing cubicles had to be dismantled and rebuilt while office and dispatch areas followed different work windows. Changes to the workstation layout and site readiness added coordination during the field sequence.
ASI’s Approach
ASI inventoried the existing components, developed workstation plans and connected installation with electrical disconnects and reconnection. Approved changes brought additional workstations and field labor into the assignment.
Project Info
- Client
- Cemex
- Location
- Ontario, California
- Work
- Workstation reuse
- Areas
- Office and dispatch
- Scopes
- Furniture and electrical
- Delivery
- Phased installation
The Reuse Plan
Start with the Components.
Build a Workable Layout.
ASI's component drawing organized panels, work surfaces and storage into workstation groups. Inventory checks and layout development connected the existing furniture to the installation sequence.

ASI workstation component layout detail
The ASI Approach
Link the Field Scopes.
Manage Each Work Window.
Furniture reuse depends on more than moving panels. ASI connected component planning, installation labor and power reconnection while coordinating separate office and dispatch work.
Existing Assets
Begin with What Can Be Reused.
Existing panels, work surfaces and storage formed the starting inventory for the workstation assignment.

Origin workstation | Before
Rebuilt Workstation Rows
Existing Assets Reassembled.
The workstation rows show the client's existing panels and furniture brought together in the Ontario workplace. The assignment joined that physical result with electrical coordination and managed changes.

Workstation rows | Completed

Rebuilt workstation groups | Completed
The Result
Connected Work Delivered.
Existing inventory put to use
The workplace plan was built around reuse of the client's existing workstation components.
Related trades coordinated
Furniture dismantling and assembly were paired with electrical disconnection and reconnection.
Different operational areas addressed
Office and dispatch work were planned as separate phases within the same assignment.
Approved changes carried through
Additional workstation requirements and labor were incorporated as the project developed.