Case Study | Decommission
Bezaire, Ledwitz & Associates Torrance Office Decommission
ASI connected workstation dismantling, electrical disconnects and wall preparation for a 2,908-RSF Torrance office exit.
Overview
The Challenge
The office exit involved connected furniture, workstation power and wall surfaces. Work had to align with the relocation crew, building noise restrictions and shared freight-elevator access.
ASI’s Approach
ASI dismantled workstations in place for Atlantic Relocation to load and transport. An on-site electrician handled cubicle power and designated disconnects. Patching, sanding and priming addressed more than 100 wall-repair locations as part of the same assignment.
Project Info
- Client
- Bezaire, Ledwitz & Associates
- Location
- Torrance, California
- Suite Area
- 2,908 RSF
- Partner
- Atlantic Relocation
- Scope
- Dismantling, electrical disconnects and wall preparation
- Status
- Completed
The ASI Approach
How the Work Was Sequenced
Field Execution
Project Gallery
The Result
Furniture Cleared and Walls Prepared
Workstation dismantling, electrical support and wall preparation were delivered within one coordinated office-exit assignment. Field photographs show cleared rooms and repaired wall locations, with the existing finishes retained.