Cisco San Francisco Phased Anchoring

Home > Projects > Cisco San Francisco Phased...
Base brackets connecting the booth assembly above the access floor.

Cisco

CASE STUDY | PHASED CONSTRUCTION EXECUTION

SCAN THE LOCATIONS. CONNECT THE INSTALLATION. ONE ACCOUNTABLE PARTNER.

At Cisco's San Francisco workplace, ASI connected concrete scanning, raised-floor anchoring and staged phone-booth installation. Changing locations and construction readiness required coordinated return visits.

View Full Case Study PDF

Two workplace phone booths during the separately sequenced installation stage.

Booth installation | In Progress

SCANLOCATION COORDINATION
ANCHORRAISED-FLOOR WORK
RETURNSTAGED INSTALLATION

Overview

This was a construction-interface assignment within an evolving workplace. ASI connected scanning, access-floor anchorage and booth installation while coordinating the return work around site readiness.

Challenge

Phone-booth anchorage had to connect through a raised access floor to the structural slab. Scan findings, revised booth locations and surrounding construction affected the sequence of underfloor work and later installation.

ASI approach

ASI coordinated scanning and anchoring crews, client-defined locations and phased mobilizations. Underfloor bracing and above-floor booth connections remained separate field packages.

Results

  • Defined anchoring stages executed
  • Raised-floor bracing documented
  • Later booth connections shown in place

Project scope and field dependencies

THE WORK BEHIND THE BOOTHS. A CONSTRUCTION INTERFACE.

Selected booth locations on the second, third and fourth floors required different field stages. Scanning, revised positioning, underfloor anchors and later booth fastening had to connect without treating every floor as the same installation.

Two workplace phone booths during the separately sequenced installation stage.

Booth installation | In Progress

Open raised access floor during scanning coordination at Cisco San Francisco, In Progress.

Raised-floor scanning | In Progress

SCANCHECK FIELD LOCATIONS
CONNECTSLAB TO BOOTH
SEQUENCERETURN INSTALLATION

Work below the finished floor

The anchoring package used channel framing, bracing and threaded rods beneath the raised access floor. Above-floor connections then tied the booths into that separately sequenced installation.

Site readiness controlled the return

Client-defined locations and scan findings required field coordination. The fourth-floor return was scheduled around booth placement and the surrounding construction sequence, including planned sprinkler work.

The ASI delivery model

CONNECT THE FIELD DEPENDENCIES. KEEP THE PHASES DISTINCT.

ASI brought the scanning and installation packages together with the client team's location decisions. Each mobilization addressed its defined anchoring stage within the wider construction environment.

SCAN

Coordinate concrete scanning

Connect location checks and scanning reports with the anchoring crew's field planning.

LOCATE

Respond to revised booth positions

Coordinate client-defined locations where scan findings required adjustment or additional scanning.

FRAME

Install beneath the access floor

Connect channel framing, bracing and rods with the separate underfloor anchoring stage.

RETURN

Fasten booths in a later stage

Keep the above-floor booth connections tied to their own return mobilization and site-readiness requirements.

LINK

Coordinate installation interfaces

Align installation planning with booth placement and the client's wider construction sequence.

The outcome

UNDERFLOOR WORK AND BOOTH CONNECTIONS. EACH STAGE IN ITS OWN CONTEXT.

The field views show the anchoring system below the access floor and later booth connections above it. Together, they explain the installation interface within the evolving workplace construction.

LOCATIONSSCAN-LED COORDINATION

Scan findings and revised positioning informed the next anchoring step.

ANCHORAGEUNDERFLOOR INSTALLATION

Channel framing, bracing and rods connected the anchoring work beneath the access floor.

CONNECTIONSLATER BOOTH STAGE

Later photographs show booth base connections within the surrounding construction environment.

Executed field stages

Defined anchoring work was carried out through separate floor-specific mobilizations.

Structural-slab interface

Concrete scanning and the anchoring package addressed the route through the access-floor assembly.

Coordinated return work

The later above-floor stage followed client booth placement and construction-readiness coordination.

Visible installation detail

Underfloor bracing and later base connections show how booth installation connects to the access-floor assembly.

ASI connected specialist scanning, location coordination and phased anchoring execution, linking the underfloor work with the later booth installation and the surrounding construction sequence.

Field execution

BELOW AND ABOVE THE ACCESS FLOOR. DISTINCT CONSTRUCTION STAGES.

Raised-floor bracing and later booth base connections show distinct stages within the workplace construction. The views connect the underfloor anchoring package with the separate above-floor installation.

Cisco San Francisco Phased Anchoring case study cover

Read the full case study.

At Cisco's San Francisco workplace, ASI connected concrete scanning, raised-floor anchoring and staged phone-booth installation. Changing locations and construction readiness required coordinated return visits.

Download PDF

One accountable partner.

CONNECT THE ANCHORING. RESPECT THE SEQUENCE.

Location decisions, below-floor installation and later booth fastening have different dependencies. ASI connected those field packages within the surrounding workplace construction.