CASE STUDY | PHASED CONSTRUCTION EXECUTION
SCAN THE LOCATIONS. CONNECT THE INSTALLATION. ONE ACCOUNTABLE PARTNER.
At Cisco's San Francisco workplace, ASI connected concrete scanning, raised-floor anchoring and staged phone-booth installation. Changing locations and construction readiness required coordinated return visits.

Booth installation | In Progress
Overview
This was a construction-interface assignment within an evolving workplace. ASI connected scanning, access-floor anchorage and booth installation while coordinating the return work around site readiness.
Challenge
Phone-booth anchorage had to connect through a raised access floor to the structural slab. Scan findings, revised booth locations and surrounding construction affected the sequence of underfloor work and later installation.
ASI approach
ASI coordinated scanning and anchoring crews, client-defined locations and phased mobilizations. Underfloor bracing and above-floor booth connections remained separate field packages.
Results
- Defined anchoring stages executed
- Raised-floor bracing documented
- Later booth connections shown in place
Project scope and field dependencies
THE WORK BEHIND THE BOOTHS. A CONSTRUCTION INTERFACE.
Selected booth locations on the second, third and fourth floors required different field stages. Scanning, revised positioning, underfloor anchors and later booth fastening had to connect without treating every floor as the same installation.

Booth installation | In Progress

Raised-floor scanning | In Progress
Work below the finished floor
The anchoring package used channel framing, bracing and threaded rods beneath the raised access floor. Above-floor connections then tied the booths into that separately sequenced installation.
Site readiness controlled the return
Client-defined locations and scan findings required field coordination. The fourth-floor return was scheduled around booth placement and the surrounding construction sequence, including planned sprinkler work.
The ASI delivery model
CONNECT THE FIELD DEPENDENCIES. KEEP THE PHASES DISTINCT.
ASI brought the scanning and installation packages together with the client team's location decisions. Each mobilization addressed its defined anchoring stage within the wider construction environment.
Coordinate concrete scanning
Connect location checks and scanning reports with the anchoring crew's field planning.
Respond to revised booth positions
Coordinate client-defined locations where scan findings required adjustment or additional scanning.
Install beneath the access floor
Connect channel framing, bracing and rods with the separate underfloor anchoring stage.
Fasten booths in a later stage
Keep the above-floor booth connections tied to their own return mobilization and site-readiness requirements.
Coordinate installation interfaces
Align installation planning with booth placement and the client's wider construction sequence.
The outcome
UNDERFLOOR WORK AND BOOTH CONNECTIONS. EACH STAGE IN ITS OWN CONTEXT.
The field views show the anchoring system below the access floor and later booth connections above it. Together, they explain the installation interface within the evolving workplace construction.
Scan findings and revised positioning informed the next anchoring step.
Channel framing, bracing and rods connected the anchoring work beneath the access floor.
Later photographs show booth base connections within the surrounding construction environment.
Executed field stages
Defined anchoring work was carried out through separate floor-specific mobilizations.
Structural-slab interface
Concrete scanning and the anchoring package addressed the route through the access-floor assembly.
Coordinated return work
The later above-floor stage followed client booth placement and construction-readiness coordination.
Visible installation detail
Underfloor bracing and later base connections show how booth installation connects to the access-floor assembly.
ASI connected specialist scanning, location coordination and phased anchoring execution, linking the underfloor work with the later booth installation and the surrounding construction sequence.
Field execution
BELOW AND ABOVE THE ACCESS FLOOR. DISTINCT CONSTRUCTION STAGES.
Raised-floor bracing and later booth base connections show distinct stages within the workplace construction. The views connect the underfloor anchoring package with the separate above-floor installation.

Read the full case study.
At Cisco's San Francisco workplace, ASI connected concrete scanning, raised-floor anchoring and staged phone-booth installation. Changing locations and construction readiness required coordinated return visits.

One accountable partner.
CONNECT THE ANCHORING. RESPECT THE SEQUENCE.
Location decisions, below-floor installation and later booth fastening have different dependencies. ASI connected those field packages within the surrounding workplace construction.