Case Study | Construction
Device Removal and Wall Restoration
ASI coordinated electrical and low-voltage removal with patching and painting at Microsoft's San Francisco workplace, managing trade handoffs within restricted evening access.
Overview
The Challenge
Room schedulers and clocks had to come out before affected wall areas could be repaired. Building access, shared ventilation and the work of separate trade crews made the sequence as important as the individual tasks.
ASI’s Approach
ASI connected device removal and electrical make-safe with patching, sanding, priming and painting. The field plan coordinated evening access and a return visit to complete the remaining finish work.
Project Info
- Client
- Microsoft
- Location
- San Francisco, California
- Site
- 555 California Street
- Work Area
- Meeting-room locations
- Delivery
- Device removal and wall repairs
- Status
- Completed
The ASI Approach
How the Work Was Sequenced
Field Execution
Project Gallery

Device location | Before

Wall repair after device removal | In Progress

Painting preparation | In Progress

Wall finish | Completed

Angled wall finish | Completed
The Result
Technical Removal and Finish Work Completed
- Devices removed from the affected locations
- Wall repairs and painting completed
- Technical and finishing scopes coordinated