Stantec Portland Office Clearance and Redistribution

Home > Projects > Stantec Portland Office Clearance...
Stantec Portland office clearance | Completed

CASE STUDY | INTEGRATED OFFICE GIVE-BACK

CONNECT THE SCOPES. CLEAR THE FLOOR. CONTROL THE ROUTES.

ASI connected office clearance with electrical and cabling interfaces, targeted patch-and-paint work, building protection, demountable-wall handling and furniture reuse and storage logistics.

View Full Case Study PDF

Stantec Portland: Integrated Office Give-Back case study cover

CLEAROFFICE-CLEARANCE PHASE
CONNECTTECHNICAL INTERFACES
ROUTEREUSE AND STORAGE

Overview

ASI provided one accountable coordination point for an integrated office give-back. The defined scope joined electrical and cabling interfaces, targeted wall and floor-service work, furniture and demountable components with building protection and material logistics.

Challenge

Stantec's Portland transition required more than removing furniture. Electrical and cabling interfaces, wall and floor-service finishes, demountable components and material routes had to connect with protected building access and retained office areas.

ASI approach

ASI brought the defined give-back scopes into one field plan. Electrical safe-off, cabling removal and targeted finishes were coordinated with dismantling, protected circulation, onsite retention, offsite storage and selected redistribution.

Results

  • Defined office-clearance phase completed
  • Technical, finish and material interfaces connected in one field plan
  • Reuse, storage and removal routes coordinated

Plans and project scale

DEFINE THE CLEARANCE AREA. CONNECT THE FIELD INTERFACES.

The workplace plans distinguish clearance boundaries, retained office areas and material-routing decisions. That spatial context connected dismantling, technical interfaces, protected access and the handling of reusable components.

The ASI delivery model

INTERACTING GIVE-BACK SCOPES. ONE COORDINATED FIELD PLAN.

The field plan connected technical safe-off, workplace dismantling, targeted finishes and material handling. Each interface had to fit the clearance boundary, retained office and protected building routes.

PLAN

Define the give-back boundaries

Connect clearance and retained areas with technical interfaces, reuse decisions, storage and removal routes.

PROTECT

Manage building access

Coordinate protected circulation, elevator and dock interfaces, and staged movements with the workplace-services partner.

SAFE OFF

Connect electrical and cable interfaces

Bring de-electrification, workstation cabling removal, entry-access safe-off and floor-service caps into the dismantling sequence.

CLEAR

Join dismantling and targeted finishes

Coordinate furniture and demountable-wall handling with wall-item removal, targeted patching and painting, and broom-clean clearance.

ROUTE

Separate reuse, storage and removal

Connect onsite retention, offsite storage, selected redistribution and disposal with the handling of reusable furniture and wall components.

The outcome

THE CLEARANCE PHASE WAS COMPLETE. THE FIELD INTERFACES WERE CONNECTED.

The defined office-clearance phase produced an open work area. Furniture and demountable components moved through coordinated retention, storage and removal routes, while existing carpet, ceiling and lighting remained part of the building environment.

Clearance completion

The defined office-clearance phase was completed, with open work areas alongside retained workplace contents.

Integrated scope coordination

Electrical and cable interfaces, targeted patch-and-paint work, and workplace dismantling shared one field plan.

Protected material movement

Building protection, circulation, dock and elevator interfaces connected the floor work with furniture and component handling.

Reuse and storage coordination

Onsite relocation, offsite storage and selected redistribution were coordinated with disposal and reusable-component handling.

Field execution

THE FIELD SEQUENCE. THE CLEARED WORKPLACE.

The field views connect the demountable-office starting condition with dismantling, completed office clearance and protected handling. Retained contents and existing finishes remain visible within the continuing workplace.

Stantec Portland: Integrated Office Give-Back case study cover

Read the full case study.

ASI gave Stantec one accountable coordination point for an office give-back that combined technical and finish interfaces, workplace dismantling, protected access and storage logistics. The completed clearance phase supported the broader workplace transition.

Download PDF

One accountable partner.

PLANNING A WORKPLACE TRANSITION?

ASI joined electrical and cabling interfaces, targeted finishes, furniture and wall handling, building protection and storage in one clearance sequence. The plan connected retained office areas with the materials leaving the floor.