Construction and Interior Renovation
Lift the furniture. Renew the finishes. Meet the window.
For Hilldrup's Pearson assignment, ASI brought painting and carpet installation together as one coordinated field operation. The lift method allowed flooring beneath retained workstations to be renewed without a full furniture relocation.
View Full Case Study PDF
Overview
Challenge
Carpet had to be replaced beneath retained workstations while painting progressed in the same suite. The compressed schedule left little room for the trades to work as separate, consecutive projects.
ASI approach
ASI sequenced protection, painting, floor preparation and lift-method carpet installation by work area, coordinating the interfaces between retained furniture, new finishes and final reset.
Results
- 7,500 sq. ft. of carpet replaced
- Over 8,500 sq. ft. of painting completed
- Both scopes delivered within the same window
Project scope
DEFINE THE FLOORING SCOPE. CONNECT THE TRADE SEQUENCE.
The carpet work areas formed part of the coordinated painting and flooring refresh.

Carpet replacement work areas
Coordinated field delivery
Sequence the shared work areas
Align material delivery, access, protection and the revised working window before the painting and flooring crews progress through the suite.
Renew the interior finishes
Prepare and paint wall surfaces and frames around retained furnishings, with final touch-ups coordinated with the floor and base work.
Install beneath retained furniture
Use the lift method to raise retained workstations for carpet access, avoiding a full furniture relocation while the flooring is renewed.
Connect preparation and installation
Remove existing carpet, address localized substrate conditions, install the new carpet and coordinate cove-base finishing.
Reset and finish the space
Coordinate rolling, cleaning, finishing details and furniture reset, then complete the documented closeout within the agreed window.
Field execution
Inside the project.
Completed work
The refreshed testing center.
The outcome
What the project delivered
The completed refresh brought 7,500 square feet of new carpet and over 8,500 square feet of renewed painted surfaces into the testing center. Both scopes were coordinated around retained workstations and the agreed four-day delivery window.

Read the full case study.