Affinity Investment Advisors Irvine Workplace Clearance
ASI coordinated connected furniture, a built platform and removal logistics for Affinity Investment Advisors’ Irvine workplace.
Overview
The Challenge
The clearance covered cubicles and office furniture in the main and adjacent suites. The assignment also included a stage, trading desks and ceiling-mounted poles. Building-access windows tied dismantling, material handling and truck movements together.
ASI’s Approach
ASI organized a three-part field assignment for furniture systems, custom workplace elements and suite cleaning. Workstation disconnection and dismantling were coordinated with supporting labor, carts and trucks. A Friday-afternoon start and weekend elevator windows shaped the removal plan.
Project Info
- Client
- Affinity Investment Advisors
- Location
- Irvine, California
- Scope
- Workplace clearance
The ASI Approach
How the Work Was Sequenced
Field Execution
Project Gallery

Cleared office area at Affinity Investment Advisors in Irvine | Completed

Built platform during dismantling at the Irvine workplace | In Progress

Cleared circulation after furniture removal | Completed

Workstation before dismantling | Before

Crew member working at a ceiling opening | In Progress

Dismantled furniture components staged on carts | In Progress

Crew handling furniture components at a truck | In Progress
The Result
Work Areas Cleared
Original project photographs document cleared workplace areas and circulation after furniture removal, along with the dismantling of workstation systems and the built platform. Existing building finishes remained in place. Construction restoration was excluded from this assignment.