Stantec Lynnwood Multi-Level Workplace Exit

Home > Projects > Stantec Lynnwood Multi-Level Workplace...
Stantec Lynnwood Multi-Level Workplace Exit case study cover

CASE STUDY | WORKPLACE DECOMMISSIONING

CLEAR THE WORKPLACE. COORDINATE THE TRADES. MANAGE THE CHANGE.

ASI coordinated furniture clearance, electrical and equipment removals, interior debranding and localized wall preparation across Stantec's Lynnwood workplace.

View Full Case Study PDF
Stantec Lynnwood Multi-Level Workplace Exit case study cover
2 LEVELSFULL + PARTIAL FLOOR
POWERSELECTIVE DISCONNECTS
PREPARELOCALIZED WALL AREAS

Overview

Challenge

The workplace exit combined large furniture-removal areas with electrical interfaces, server-room equipment and wall preparation. Elevator access, staggered crews and added contents required coordinated field logistics.

ASI approach

ASI organized the clearance and hauling sequence around building access, coordinated selective technical removals and incorporated additional items left for removal into the field scope.

Results

  • Furniture and designated contents cleared
  • Selective technical removals completed
  • Localized wall surfaces prepared

Workplace layout and removal planning

READ THE WORKPLACE. ORGANIZE THE EXIT.

The historical fourth-floor furniture layout shows the offices, workstation groups and circulation behind the clearance assignment. It provides planning context for the workplace footprint.

Historical fourth-floor furniture layout | Planning context only

Historical fourth-floor furniture layout | Planning context only

Coordinated field delivery

CONTROL THE MOVEMENT

Elevator availability and reserved access shaped the removal plan. ASI coordinated staggered crews, handling equipment, vehicles and disposal capacity as the workplace was cleared.

ABSORB THE ADDED SCOPE

Items originally designated for staff removal or donation remained when field work began. ASI incorporated their removal with additional labor, containers and disposal coordination.

The outcome

THE WORKPLACE CLEARED. THE LOCAL INTERFACES ADDRESSED.

ASI coordinated the Lynnwood workplace exit across furniture, technical equipment, interior signage and localized surface preparation, adapting the removal scope as additional contents remained on site.

Multi-level field logistics

Crew staging, elevator access and hauling were organized around the building's movement requirements.

Expanded contents removal

Additional items left for removal were incorporated into the labor, container and disposal plan.

Technical coordination

Selective power disconnection and equipment removal were coordinated alongside the furniture exit.

Localized preparation

Interior debranding and repair of affected wall areas supported the transition of the vacated workplace.

Field execution

CLEARANCE ACROSS THE WORKPLACE. PREPARATION AT THE INTERFACES.

Cleared office and mezzanine views show the furniture-removal scope. Equipment-room and wall views show the local interfaces addressed while retained building systems and finishes remain in place.

Stantec Lynnwood Multi-Level Workplace Exit case study cover

Read the full case study.

Download PDF

One accountable partner.

PLANNING A MULTI-LEVEL WORKPLACE EXIT?

ASI brought clearance, selective technical work and surface preparation together under one coordinated workplace-exit assignment.

Start a Project

Ready to Move Your Project From Plan to Field?