Stantec Tucson Office and Exterior Closeout

Home > Projects > Stantec Tucson Office and...
Stantec

Case Study | Selective Office Closeout and Elevated Sign Removal

Inside the Office.
Above the Street.
One Coordinated Exit.

ASI connected selective interior decommission, technical-room responsibilities and elevated building-sign removal for Stantec's Tucson office exit at 5151 E Broadway Boulevard, Suite 400.

View Full Case Study PDF

Cover of the Stantec Tucson Office and Exterior Closeout case study

Overview

The Challenge

The assignment reached beyond the suite interior. Interior removals and specialty sign work had separate access windows. Weekday removal restrictions, a designated elevator and controlled building entry had to be coordinated alongside retained furniture and building systems.

ASI’s Approach

ASI tied office clearance to removal of designated wall-mounted items and associated patching, preparation and priming. The technical-room scope included electrical disconnection, rack decommission and e-waste handling while retaining the room's air-conditioning system.

Project Info

Client
Stantec
Location
Tucson, Arizona
Site
5151 E Broadway Boulevard
Suite
400
Delivery
Selective office decommission and elevated building-sign removal
Status
Completed scope

The Office Footprint

Existing Suite 400 Layout.

Existing origin office layout for Stantec Tucson at 5151 E Broadway Boulevard, Suite 400.

Existing office layout

Selective Closeout Within the Existing Office

The origin-site layout places the closeout within the Suite 400 workplace. Designated contents were cleared while retained workstations, fixed counters and building elements remained distinct from the removal scope.

The ASI Approach

Interior and Exterior Responsibilities, Connected.

Coordinate the building windowsAlign interior removal restrictions, the designated elevator and controlled entry with separate specialty sign work.
Clear the designated office contentsConnect selective clearance with removal of assigned wall-mounted items and their patching, preparation and priming.
Keep technical responsibilities boundedCoordinate electrical disconnection, racks and e-waste within the technical-room assignment while retaining its air-conditioning system.
Connect rooftop and exterior interfacesAccount for rooftop power and disconnection requirements before the specialty sign crew arrived.
Carry the sign work through verificationUse specialty suspended access for the building-mounted sign, address its attachment points and complete the exterior verification with the building engineer.

Elevated Building-Sign Removal

One Building-Mounted Sign.

Specialty suspended access brought the crew to the upper facade. The building-mounted sign was removed and its attachment points addressed, with building-engineer verification of the exterior work.

Stantec building-mounted sign before removal, with the upper facade visible.

Building sign | Before

Upper facade with the building-mounted Stantec sign removed.

Building-mounted sign removed | Completed

Selective Interior Closeout

Clear What Is Designated. Retain What Stays.

Designated office contents were cleared while fixed counters, retained workstations and existing floor finishes remained.

Resource room with office contents before selective clearance.

Resource room | Before

Cleared resource room with retained counters and shelving.

Resource room | Completed

Workstation area with boxes and office contents before selective clearance.

Workstation area | Before

Cleared workstation area with retained panels, desks and chair.

Workstation area | Completed

The Result

One Coordinated Workplace Exit.

Inside the office, designated contents were cleared while retained workstations, fixed counters and existing floor finishes remained. Outside, the building-mounted sign was removed and its attachment points addressed. ASI connected the interior, technical and exterior responsibilities through one coordinated workplace-exit assignment.

All Solutions, Inc.

Planning an Office Exit With Exterior Scope?

Connect selective decommission, technical responsibilities and specialty access through one accountable project partner.