Stantec Boston Causeway Decommissioning

Home > Projects > Stantec Boston Causeway Decommissioning
Office removal interface | In Progress

CASE STUDY | OFFICE DECOMMISSIONING

CLEAR THE WORKPLACE. DEFINE THE BOUNDARIES. CONNECT THE SCOPES.

ASI connected office clearance, technical disconnection and targeted repair requirements at Causeway, with retained building features clearly defined.

View Full Case Study PDF

Stantec Boston Causeway Decommissioning case study cover | In Progress

CLEARWORKPLACE CONTENTS
SCOPETRADE INTERFACES
KEEPRETAINED ELEMENTS

Overview

The Causeway package joined office clearance with technical and finish interfaces. Broad open areas, a cleared office and the retained reception show different parts of the same workplace.

Challenge

Office decommissioning requires a clear distinction between contents to remove, services to disconnect, surfaces to address and building features to retain. At Causeway, those requirements shared one sixth-floor workplace.

ASI approach

ASI grouped contents, electrical, low-voltage and repair requirements within the same decommissioning assignment, with retained features and floor-repair exclusions kept explicit.

Results

  • Broad workplace areas cleared
  • Distinct removal interfaces visible
  • Retained reception and building features

Workplace scale and retained conditions

CLEAR THE OFFICE CONTENTS. DEFINE WHAT STAYS.

The open-office views show the clearance footprint. Retained cabinetry, tackboards, reception and brick context make the removal boundaries important alongside the assigned technical and repair scopes.

Open-office clearance | In Progress

Open-office clearance | In Progress

CONTENTSDISMANTLING AND CLEARANCE
SERVICESELECTRICAL AND CABLING
BOUNDARIESRETAINED BUILDING ELEMENTS

CONNECTED REMOVAL REQUIREMENTS

The package covered furniture, fixtures, electronics and remaining contents, with cubicle-power disconnections, low-voltage removal back to the nearest riser room and e-waste requirements.

DEFINED RETAINED CONDITIONS

Brown tackboards, the reception station, brown wall and brick were excluded from removal. Floor cores and floor repair were also outside the Causeway scope, keeping those boundaries distinct from the assigned wall and ceiling work.

The ASI delivery model

CONNECT THE REMOVAL SCOPES. KEEP THE LIMITS CLEAR.

ASI's Causeway package combined contents removal with electrical, low-voltage and targeted finish requirements. The same scope distinguished retained features from the items assigned for removal.

CLEAR

Address workplace contents

Include furniture, fixtures, electronics, remaining items, broom sweeping and e-waste requirements in the clearance package.

POWER

Define electrical disconnections

Link cubicle and other required power disconnections with the affected contents-removal areas.

CABLE

Set the cabling-removal boundary

Carry low-voltage removal back to the nearest riser room within the decommissioning requirements.

PATCH

Connect removal and finish work

Include targeted wall/surface patching and ceiling repair at removed mounting points, lockers and hang track.

KEEP

Respect retained-building limits

Keep retained brown tackboards, reception, brown wall, brick and excluded floor work distinct from the removal package.

The outcome

WORKPLACE CLEARANCE VISIBLE. REMOVAL BOUNDARIES DEFINED.

Broad cleared office areas show the contents-removal phase. Retained reception and building features remain visible, while electrical, cabling and targeted repair requirements formed part of the defined assignment.

Office clearance

Open workplace areas and a separate office show the removal phase at the exact Causeway site.

Technical requirements

Electrical disconnections and low-voltage removal limits were carried in the same assigned package.

Targeted finish interfaces

Wall, surface and ceiling repair requirements addressed the interfaces created by specified removals.

Retained-feature boundaries

Reception, brown tackboards, brown wall and brick were excluded from removal, with floor work separately excluded.

Field execution

OFFICE CLEARANCE. DEFINED BUILDING INTERFACES.

The Causeway views show two broad workplace relationships, a cleared office and the retained reception. Ceiling gaps, surface differences and existing flooring remain part of the depicted work phase.

Stantec Boston Causeway Decommissioning case study cover | In Progress

Read the full case study.

ASI brought contents removal, technical disconnection requirements and targeted repair into one Causeway decommissioning assignment. Retained-feature and floor-work exclusions kept the scope boundaries explicit.

Download PDF

Explore Stantec's national workplace program

One accountable partner.

PLANNING AN OFFICE DECOMMISSIONING?

Contents clearance, service-removal requirements and targeted repair belonged to one Causeway assignment. Explicit retained-feature exclusions defined the boundary between removing the workplace contents and changing the surrounding building.